Data Centers

JDRM Engineer’s data center experience includes designing data centers providing geo-redundancy as well as the first Green Data Center in a University in Ohio. Our expertise spans in-row cooling and redundant systems, underfloor air distribution, fire suppression systems and more across the entire spectrum of organizational needs, from healthcare to industrial, educational to corporate internet/phone/entertainment providers. Our technological capabilities and experience empowers our clients to do more and be more for their clients.

Check out our Case Study for Magna where we consolidated multiple data centers into a tight space in their new corporate office building.

Fortune 500 Company

Corporate data center for worldwide business unit

5,000 sq ft of data center ‘white’ space

  • Raised floor with redundant HVAC
  • Redundant uninterruptible power system (UPS)
  • Redundant power distribution

Single generator with provisions to add second

Single building electrical utility service with provisions for future second utility service

Redundant mechanical systems; multiple CRAC/Drycooler systems

Building also serves as corporate office facility

Building system design provisioned for upgrades to meet Tier IV compliance

Internet, Communications and Entertainment Provider – World Headquarters

Major Service Provider

Building designed to withstand F5 tornado

Electrical System Upgrade

  • Single electrical utility service to provide fully redundant transformer capacity

Emergency generation system design included:

  • 100% redundant generator back up (2N design) for parallel operation
  • Multiple automatic transfer switches for redundant power distribution

Mechanical system upgrades included:

  • Addition of 100% redundant air cooled chiller incorporating waterside economizer with free-cooling component designed for extreme low temperature operation
  • Redundant chilled water system pumps with VFD’s
  • Expansion of building chilled water loop to accommodate extension
  • Phased approach to data center cooling upgrades
  • In-row chilled water cooling with containment implemented in data center to supplement and enhance existing air handling system
  • DCIM software system implemented for data center utility monitoring

Internet, Communications and Entertainment Provider – GeoRedundancy/Expansion Facility

Local Service Provider to new geo-redundant data center

  • Building designed to withstand F5 tornado
  • Existing 3,900 sq ft computer room ‘white’ space
  • Existing redundant air handling systems in electrical/service spaces
  • Existing data center provisioned with redundant CRAC/Drycooler systems.

Long term planning includes

Mechanical

  • Replacement of existing CRAC/Drycoolers with central chilled water plant (100%) redundant air cooled chillers with waterside economizer for low ambient operation and free-cooling opportunities
  • Computer space reconfigured with in-row cooling, hot/cold aisle configuration and hot aisle containment
  • DCIM incorporated into space and utility monitoring

Electrical

  • Upgrade building electrical service to permit installation of redundant transformers
  • Design of 100% emergency generation redundancy
  • Design of complete A/B electrical distribution throughout the Data Center and all critical equipment components

Building

  • Incorporation of complete building automation/monitoring system upgrade to provide enterprise level of service
  • Incorporation of complete building access control and CCTV system upgrades to provide enterprise level of service and remote monitoring
  • Biometrics and multilevel of building access/security provisions
  • Existing Halon fire protection system will be upgraded with new FM200 system

The University of Toledo

2010 Health Science and Main Campus Upgrades

Data center capacity was increased to meet increasing demands; the campus’ were connected via a fiber optic direct communication link providing network system redundancy.

Mechanical System Upgrades

Health Science Campus

  • Existing HVAC systems were made of redundant CRAC units connected into building/hospital central chilled water plant
  • New electrical room was provided with redundant air handling units connected into existing building chilled water system
  • Existing underfloor air distribution was enhanced by re-positioning floor supply grilles
  • Data cabinets were replaced and provided with dedicated exhaust connection into return air plenum
  • Existing CRAC units were updated to include extension of return air ductwork into ceiling plenum
  • Computer room ceiling was reconfigured to include return air provisions over the hot aisles as well as to incorporate dedicated data cabinet exhaust discharge

Main Campus

  • Existing Computer Room incorporates 2 CRAC units connected into building central chilled water system and 2 CRAC units with dedicated drycoolers.
  • Capacity is believed to be 100% redundant
  • Existing CRAC units utilized ceiling plenum with relief thru existing ceiling into the space
  • Further system modifications were deferred to future phases

Electrical System Upgrades

Health Science Campus

  • Emergency generation system design included provisions for 2 generators to operate in parallel; however, for this phase, only 1 generator was provided.
  • Dedicated emergency feeder from generator to new automatic transfer switch and distribution for Computer Room
  • Future space allocation has been identified for 2nd generator and paralleling switchgear
  • Computer Room electrical system was upgraded to include;
  • 1 new UPS with provisions for 2nd to parallel
  • Complete A/B buss power distribution thru new harmonic mitigating transformers, distribution equipment to overhead buss distribution to data cabinets

Building

Health Science Campus

  • Room data cabinets were re-organized to provide complete hot-cold aisle configuration
  • Computer room fire protection was upgraded to new FM200 system

2016 Main Campus Upgrades

Data center re-configured complete with new cabinets, power distribution, cooling and more over a phased project implementation

Room configuration updated to hot/cold aisle arrangement; in-row cooling; hot aisle containment; end of row power redundant distribution; removal of raised floor; replacement of fire protection system; provision of dedicated computer room cooling system; implementation of DCIM throughout data center

Mechanical System Upgrades

  • Existing CRAC units replace in a phase fashion due to room phased implementation.
  • Dedicated new air cooled chiller(s) designed to be 100% redundant and include waterside economizer for free-cooling and low ambient operation
  • New piping, pumps, make-up, controls to permit isolated operation
  • Computer room incorporates in-row chilled water unit solution with hot aisle containment for module and space control.  Design to provide 2N design at chiller level and N+1 design at the row/module level.
  • Dedicated computer room temperature/building automation system communicates with University and dedicated DCIM software for total system and space monitoring.

Electrical System Upgrades

  • Implementation of 2nd UPS unit for incorporation into existing parallel system design.  Capacity will provide 100% redundancy.
  • Expansion of existing battery monitoring system to new UPS
  • Installation of 2nd emergency generator to provide selectivity and 100% building redundancy.

New Computer Room electrical distribution to incorporate

  • Dedicated independent A/B services to in-row cooling units
  • Dedicated independent service to chillers from separate transfer switch distribution
  • Dedicated independent A/B services to end of row power distribution units (one on each end of row)
  • Dedicated and independent local power distribution for legacy equipment and local power needs in the computer room
  • All electrical, not including row power distribution units, are located outside of the computer room space
  • Room lighting upgrades to incorporate LED lighting and strategic switching to accommodate flexibility and energy saving opportunities.
  • Room grounding system will be enhanced to accommodate proposed room re-configuration

Building Upgrades

  • Computer Room access floor removed
  • Computer room ceiling replaced
  • Computer Room fire protection system upgraded