First Solar PGT 4 Substation

Perrysburg, Ohio

Electrical

The site/building projected electrical demand indicates that the site would require a Customer Owned substation.

The substation was designed to provide a 138kV to 12.47kV transformation via 2-30 MVA transformers.

The substation was developed in concert with a Utility Detailed Load Study and their recommendations and requirements for design.

Items that were included are:

  • Primary 145kV dead tank circuit breaker
  • High Speed Ground Switch
  • Primary Utility revenue metering CT’s/PT’s
  • Provisions for CCVT’s (provides ability for Customer to install on-site generation in the future)
  • Overhead busway
  • Transformer 145kV primary dead tank circuit breaker (Each transformer)
  • 30MVA transformer and associated devices
  • 2-3000A 15kV distribution switchgear (each transformer)
  • All relay and protection settings for 15kV circuits
  • Coordination of all protection elements with Utility metering and protection departments
  • Witness and coordination with Utility and 3rd Party Commissioning
  • 14 – 15kV distribution feeder loops that provide a redundant loop thru the site and building power distribution requirements.

Project Details

JDRM Engineering provided mechanical, electrical and technology engineering services for a new R & D Facility of approximately 1.5MM sq ft that included R & D spaces, central plant, office, warehouse/shipping, etc. spaces. The overall site power requirements required services via an onsite utility transmission level substation to develop sufficient medium voltage power for the site/campus needs.
Services
Electrical